Tuesday, January 31, 2012

About A House - Foundation Phase

It's not a very exciting time of the project at the moment & January is probably the worst month to lay a foundation.

It's Jan 31, 2012. Another non-stop rainy and soggy day in Vancouver. Foundation work started on January 9th and should take about 3 weeks if the weather cooperates. Unfortunately, sub-zero temperature snowy condition arrived mid January followed by a week of rain.

Progress as of Jan 30...

View from front of house... lots of material waiting to participate in the fun!


From back of the house


Arthur the builder, figures we need 3 dry days to finish constructing the frame of the foundation and 3 warm and dry days to pour the concrete. Warm means above +5 for at least 6 hours.

So here's to praying to the weather God to hold on that 14 days forecast! (Courtesy of The Weather Network)